A (preparatory) actions

C (content) actions

D (monitoring) actions

E (publicity) actions

F (project management) actions

2028

Planned

15.05.2028

Recommendations for the transposition of the developed system in regulatory legislation.

Responsible partner

Activity C2 "Development of tools and piloting circularity solutions for construction process and material flows".

30.06.2028

Ziņojums par statistikas datiem par preču atkārtotu izmantošanu un labošanu

Responsible partner

C7 aktivitāte "Ekosistēmas izveide, lai veicinātu atkārtotas izmantošanas, remonta un pārstrādes aktivitātes".

31.10.2028

Synthesis report on supporting capacity building and public awareness activities implemented within Action C8

Responsible partner

Activity E2 Awareness raising and capacity building.

31.10.2028

Synthesis report on supporting capacity building and public awareness activities implemented within Action C7

Responsible partner

Activity E2 Awareness raising and capacity building.

31.10.2028

Synthesis report on supporting capacity building and public awareness activities implemented within Action C5

Responsible partner

Activity E2 Awareness raising and capacity building.

31.10.2028

Synthesis report on supporting capacity building and public awareness activities implemented within Action C4

Responsible partner

Activity E2 Awareness raising and capacity building.

31.10.2028

Synthesis report on supporting capacity building and public awareness activities implemented within Action C3

Responsible partner

Activity E2 Awareness raising and capacity building

31.10.2028

Synthesis report on supporting capacity building and public awareness activities implemented within Action C2

Responsible partner

Activity E2 Awareness raising and capacity building.

31.10.2028

Synthesis report on supporting capacity building and public awareness activities implemented within Action C10

Responsible partner

Activity E2 Awareness raising and capacity building.

31.10.2028

Synthesis report on supporting capacity building and public awareness activities implemented within Action C1

Responsible partner

Activity E2 Awareness raising and capacity building.

31.10.2028

A synthesis report on the networking activities with LIFE and non-LIFE projects

Responsible partner

Activity E3 Experience exchange and networking.

31.10.2028

1 report from the Final Conference including agendas, presentation, participant list, photos.

Responsible partner

Activity E1 Project visibility and dissemination of project results.

30.11.2028

Datasets for local municipalities and national/international institutions on marine litter accordingly internationally approved methodology

Responsible partner

Activity C9 "Educational and behaviour change demonstration activities for waste prevention, sustainable consumption and circular thinking".

31.12.2028

Report on Demonstration and pilot activities replicated in the neighbouring countries

Responsible partner

Activity C11 "Development and implementation of project Replicability and Transferability Strategy".

31.12.2028

Final monitoring report

Responsible partner

Activity D1 "Monitoring of the impact of the Project results and methods demonstrated".

31.12.2028

Final monitoring report

Responsible partner

Activity D3 "Monitoring of the socio-economic impacts of the Project Actions".

31.12.2028

Educational posters on cigarette butt content, pollution, proper handling, etc (1 set of posters each year on different thematic issues) (C9)

Responsible partner

Activity E1 Project visibility and dissemination of project results.

31.12.2028

Audit report

Responsible partner

Activity F1 "Overall Project management".

31.12.2028

A Layman’s report in Latvian and English

Responsible partner

Activity E1 Project visibility and dissemination of project results.

Done